This blog is dedicated to enhance existing communication between Project Management and the Developer/Owners as well as the various trades and Subcontractors involved in the project. Access to this blog is at your convenience and the information and photos are kept current.

Wednesday, August 27, 2008

Centerpoint's track-hoe with building 144-149 in the background




Posted by Elk Mountain at 6:52 PM

No comments:

Post a Comment

Newer Post Older Post Home
Subscribe to: Post Comments (Atom)

  • Drawings 144-149 (6 plex)

Elk Mountain Flickr

  • Oct 20-25
  • Oct 6-11
  • Sept 30-Oct 4
  • Sept 21-26
  • Sept 15-20
  • Sept 1-6
  • Aug 25-30
  • Aug 18-23
  • Aug 11-17
  • Aug 4-10
  • Oct 6-11

Schedule

June 12- Centerpoint starts the excavation
June 17- Chris Robinson Construction starts the footings
June 27- Matt Funk pours concrete for exterior walls
July 7- started the underground plumbing
July 9- flat work for basement
July 11- Centerpoint Construction backfilled the foundation
July 14- lumber delivered
July 15- Wright Angle and Precision Contractong begins framing
July 18- stood main floor walls
July 28- sheeted upper floor
Aug 4- set the trusses on all units
Aug 6- sheeting the roof begins
Aug 7- Western Mechanical starts HVAC
Aug 11-Durrant Slate plumbing and Brandon Nelson begin electrical and plumbing
Aug 11-trenching for electric utilities
Aug 14-Fairway Glass begins window installation
Aug 18-roof dried in
Aug 19-Durrant Slate completes plumbing
Aug 20-AR Aluminum starts on the exterior
Aug 21- Wright Angle and Precision Contracting finishes framing / Brandon Nelson finishes electrical
Aug 25- trenched and shaded electrical utilities
Aug 26- Comcast Cable starts and finished in one day
Aug 27- Western Mechanical completes HVAC. Highpoint roofing begins shingles
Aug 29- Highpoint roofing finishes. Fairway Glass finishes window installation. LeGrand Johnson Construction starts to grade the roadways. 4-way inspection
Sept 2-Garner Construction starts the sidewalk on 1300 East
Sept 4-Stock insulation starts
Sept 5- Stock insulation complete. Brandon Nelson Electric pulls the high Voltage wire through conduit for Hyrum City
Sept 10- Questar gas installs gas lines
Sept 16- Cronquest drywall begins sheetrock
Sept 23- AR Aluminum finishes installation of the Weatherboard
Sept 29- AR Aluminum starts the exterior painting
Oct 6- Mike Garners cement crew does the porch caps
Oct 10- Precision Contracting starts the finish work

The following are pictures from building 144-149 (6 plex) Aug 25-30














sheetrock

sheetrock


siding

siding

Legrand Johnson on the retention pond

Legrand Johnson on the retention pond

elk mountain

elk mountain

Centerpoint trucks

Centerpoint trucks
Contact information:

Precision Contracting
/ Elk Mountain
PO Box 338 Hyrum, Utah 84319
Scott Hales
phone: (435) 730-7375


Blog Archive

  • ►  2009 (5)
    • ►  March (5)
  • ▼  2008 (18)
    • ►  December (1)
    • ►  October (5)
    • ►  September (7)
    • ▼  August (5)
      • Centerpoint's track-hoe with building 144-149 in t...
      • This past week has been quite eventful. Some major...
      • It is exciting when you realize how much has been ...
      • The Photos and Major Milestone dates reported on t...